Army and Military Camps
Independent Wind & Solar Hybrid Power Supply System Solution for Army and Military Camps
Case: Island Frontier Sentry independent wind & solar hybrid power supply system solution.
Usage of environmental resources: (annual average wind rate approx 6.7m/s, annual sunshine duration about
2, 300hrs)
System scheme configuration: FSHD-70K
Configuration Specification Quantity
Wind turbine generator system 10KW/DC240V 5 sets
Solar panel 200W/DC24V 100 pcs
Blower fan controller 10KW/240V 5 sets
Solar energy controller 2KW/240V 10 sets
Inverter DC240V-AC380V(50HZ)-50KW 1 set
Battery 200AH/DC12V 120 pcs
Independent tower pole 12m 5 sets
Cable conductor Provide as requested
System average generating capacity/day 210KWH
Load power consumption 20KW, 8hrs/day 160KWH
Annual coal consumption saved 30.967t
Annual exhaust emission reduced 82.681t
Functions achieved: Satisfying total power consumption load of 20KW in island armies, daily running 8hrs, enabling normal running at least two days under no wind and light.
The system can be in service without problems for 15 to 20 years, suitable for defined system technical proposals of independent power supply for Wind-solar energy army and
Military camps in different regions. We can provide proper design services according to natural resources in the applied regions and user demands.